Direct-to-chip cooling captures heat at selected components
In a typical single-phase system, heat travels from GPUs and CPUs through thermal interface material into cold plates. A supply manifold distributes coolant to the servers and a return manifold collects warmer fluid. In a liquid-to-liquid design, a coolant distribution unit (CDU) transfers heat from the technology cooling system (TCS) to the facility water system (FWS).Memory, network adapters, storage and power supplies may still depend on airflow. Ask the server supplier for liquid heat capture and residual air load at the proposed configuration and workload. Use the captured heat load to size the liquid loop and the residual air load to size room cooling.
Check the hydraulics as well. A rack can receive its specified total flow while a server on a higher-resistance branch gets too little. Verify minimum flow at each branch and check available pump head against losses through cold plates, hoses, quick disconnects, valves, manifolds and filters along the limiting path.
Immersion cooling collects heat in a dielectric fluid
Immersion places compatible hardware in direct contact with electrically insulating fluid. In single-phase systems, the liquid warms and transfers heat to a heat exchanger. In two-phase systems, fluid boils at hot surfaces and a condenser returns the vapor to liquid. Both need a downstream heat rejection path.Tank capacity describes heat removal under specified conditions. Verify critical component temperatures under sustained load at the intended tank population. Confirm hardware and wetted-material compatibility with the exact fluid, along with warranty coverage, filled tank floor loading, lifting clearance and the service procedure for removing hardware.
| Engineering check | Direct-to-chip | Immersion |
| Heat load | Verify cold plate heat capture and residual air load. | Verify tank capacity and heat from equipment outside the bath. |
| Local limits | Check branch flow and server inlet temperature. | Check critical component temperatures under sustained load. |
| Facility interface | Check supply temperature, flow and pressure at the CDU. | Check the requirements of the heat exchanger, CDU or condenser. |
| Service | Verify branch isolation and reconnection. | Verify lifting, fluid handling and return to service. |
How to Size a Coolant Distribution Unit (CDU)
A liquid-to-liquid CDU typically separates the facility and technology circuits with a heat exchanger. Pumps circulate technology-side coolant, and sensors and controls track operating conditions and report faults. A liquid-to-air CDU transfers the captured heat to an air stream, so the room cooling design must account for that load.Compare CDU ratings at the intended operating point. Record facility inlet temperature and flow, required technology-side supply temperature and flow, fluid properties and available pump head. A 30°C facility-water inlet and a required 32°C technology-side outlet give a 2°C approach at the cold end. Ask the supplier to demonstrate the required capacity at that approach and the proposed flow rates.

Worked example: 90 kW on the technology loop
For single-phase cooling, heat transfer equals mass flow multiplied by specific heat capacity and coolant temperature rise. Assuming water at approximately 4.18 kJ/(kg·K) and a density near 1 kg/L, a 90 kW load at a 10°C temperature rise requires 90 ÷ (4.18 × 10) ≈ 2.15 kg/s, or 129 L/min. At a 5°C rise, the flow doubles to about 258 L/min.For glycol or dielectric fluid, use properties at the design temperature. Specific heat and density affect the flow calculation, while viscosity affects pressure drop. Check the equipment’s flow limits and the pump curve against the system pressure drop. Where redundancy is specified, verify the available flow with the designated unit out of service.
What to verify during commissioning
Agree the operating limits and pass criteria before testing. Run a representative workload until temperatures and performance stabilize. Collect cooling telemetry and workload results over the same time window.1. Record IT power, coolant supply and return temperatures, and flow. Compare calculated heat removal with the design heat split, allowing for measurement uncertainty and other heat inputs within the measurement boundary.
2. Check branch flow and server inlet temperature at the most constrained cold-plate equipment. For immersion, verify critical component temperatures at the intended tank population.
3. If redundancy is specified, follow the approved commissioning procedure to check remaining flow, alarms and workload behaviour during changeover.
4. Walk through a hardware replacement and agree which checks must be repeated before return to service.
If you’re preparing a liquid-cooled GPU deployment, bring your server cooling requirements, the facility’s available supply conditions and the proposed CDU or immersion tank specifications to Advange’s AIDC team. We can help you identify what the equipment supplier and facility operator need to confirm, agree what to measure during acceptance testing and define who will respond to cooling alarms after handover. Those checks give your operations team a baseline for running and expanding your AI infrastructure.